Photo: mike evansThe Associated Press has a blockbuster study of the Nuclear Regulatory Commission (NRC):
Federal regulators have been working closely with the nuclear power industry to keep the nation’s aging reactors operating within safety standards by repeatedly weakening those standards, or simply failing to enforce them, an investigation by The Associated Press has found.
Time after time, officials at the U.S. Nuclear Regulatory Commission have decided that original regulations were too strict, arguing that safety margins could be eased without peril, according to records and interviews.
The result? Rising fears that these accommodations by the NRC are significantly undermining safety — and inching the reactors closer to an accident that could harm the public and jeopardize the future of nuclear power in the United States.
I’ve been arguing for a long time that there was no nuclear renaissance, that the industry had failed to get its act in order, and had priced itself out of the market. Then back in October, Exelon CEO John Rowe explained that low gas prices and no carbon price push back nuclear renaissance a “decade, maybe two.” In short, nuclear power has gone from “too cheap to meter” to “too costly to matter.”
The meltdown in Japan pulled back the veil on the grim underlying economics of nuclear power and certainly killed the myth that we can afford to skimp on review, oversight, and safety in an effort to save money.
Now the AP has revealed that the kind of lax oversight common in Japan is apparently common in this country, too. Here’s more from the AP’s sobering, must-read analysis:
Examples abound. When valves leaked, more leakage was allowed — up to 20 times the original limit. When rampant cracking caused radioactive leaks from steam generator tubing, an easier test of the tubes was devised, so plants could meet standards.
Failed cables. Busted seals. Broken nozzles, clogged screens, cracked concrete, dented containers, corroded metals and rusty underground pipes — all of these and thousands of other problems linked to aging were uncovered in the AP’s yearlong investigation. And all of them could escalate dangers in the event of an accident.
Yet despite the many problems linked to aging, not a single official body in government or industry has studied the overall frequency and potential impact on safety of such breakdowns in recent years, even as the NRC has extended the licenses of dozens of reactors.
Industry and government officials defend their actions, and insist that no chances are being taken. But the AP investigation found that with billions of dollars and 19 percent of America’s electricity supply at stake, a cozy relationship prevails between the industry and its regulator, the NRC.
Records show a recurring pattern: Reactor parts or systems fall out of compliance with the rules. Studies are conducted by the industry and government, and all agree that existing standards are “unnecessarily conservative.”
Regulations are loosened, and the reactors are back in compliance.
“That’s what they say for everything, whether that’s the case or not,” said Demetrios Basdekas, an engineer retired from the NRC. “Every time you turn around, they say ‘We have all this built-in conservatism.’ “
Leading scientists have warned us for years that U.S. nuclear safety oversight is far from adequate. But to no avail.
Commercial nuclear reactors in the United States were designed and licensed for 40 years. When the first ones were being built in the 1960s and 1970s, it was expected that they would be replaced with improved models long before those licenses expired.
But that never happened …
Instead, 66 of the 104 operating units have been relicensed for 20 more years, mostly with scant public attention. Renewal applications are under review for 16 other reactors.
By the standards in place when they were built, these reactors are old and getting older. As of today, 82 reactors are more than 25 years old.
The AP found proof that aging reactors have been allowed to run less safely to prolong operations. As equipment has approached or violated safety limits, regulators and reactor operators have loosened or bent the rules.
Last year, the NRC weakened the safety margin for acceptable radiation damage to reactor vessels — for a second time. The standard is based on a measurement known as a reactor vessel’s “reference temperature,” which predicts when it will become dangerously brittle and vulnerable to failure. Over the years, many plants have violated or come close to violating the standard.
As a result, the minimum standard was relaxed first by raising the reference temperature 50 percent, and then 78 percent above the original — even though a broken vessel could spill its radioactive contents into the environment.
The AP’s analysis was remarkably thorough:
The AP collected and analyzed government and industry documents — including some never-before released. The examination looked at both types of reactor designs: pressurized water units that keep radioactivity confined to the reactor building and the less common boiling water types like those at Fukushima, which send radioactive water away from the reactor to drive electricity-generating turbines.
Tens of thousands of pages of government and industry studies were examined, along with test results, inspection reports and regulatory policy statements filed over four decades. Interviews were conducted with scores of managers, regulators, engineers, scientists, whistleblowers, activists, and residents living near the reactors, which are located at 65 sites, mostly in the East and Midwest.
AP reporting teams toured some of the oldest reactors — the unit here at Oyster Creek, near the Atlantic coast 50 miles east of Philadelphia, and two units at Indian Point, 25 miles north of New York City along the Hudson River.
Called “Oyster Creak” by some critics because of its aging problems, this boiling water reactor began running in 1969 and ranks as the country’s oldest operating commercial nuclear power plant. Its license was extended in 2009 until 2029, though utility officials announced in December that they’ll shut the reactor 10 years earlier rather than build state-ordered cooling towers. Applications to extend the lives of pressurized water units 2 and 3 at Indian Point, each more than 36 years old, are under review by the NRC.
Unprompted, several nuclear engineers and former regulators used nearly identical terminology to describe how industry and government research has frequently justified loosening safety standards to keep aging reactors within operating rules. They call the approach “sharpening the pencil” or “pencil engineering” — the fudging of calculations and assumptions to yield answers that enable
plants with deteriorating conditions to remain in compliance.“Many utilities are doing that sort of thing,” said engineer Richard T. Lahey Jr., who used to design nuclear safety systems for General Electric Co., which makes boiling water reactors. “I think we need nuclear power, but we can’t compromise on safety. I think the vulnerability is on these older plants.”
Here’s some specifics from “agency staff, plant operators, and consultants … in little-known reports, where evidence of industry-wide problems is striking”:
- The AP reviewed 226 preliminary notifications — alerts on emerging safety problems — issued by the NRC since 2005. Wear and tear in the form of clogged lines, cracked parts, leaky seals, rust and other deterioration contributed to at least 26 alerts over the past six years. Other notifications lack detail, but aging also was a probable factor in 113 additional alerts. That would constitute up to 62 percent in all. For example, the 39-year-old Palisades reactor in Michigan shut Jan. 22 when an electrical cable failed, a fuse blew, and a valve stuck shut, expelling steam with low levels of radioactive tritium into the air outside. And a one-inch crack in a valve weld aborted a restart in February at the LaSalle site west of Chicago.
- One 2008 NRC report blamed 70 percent of potentially serious safety problems on “degraded conditions.” Some involve human factors, but many stem from equipment wear, including cracked nozzles, loose paint, electrical problems, or offline cooling components.
- Confronted with worn parts that need maintenance, the industry has repeatedly requested — and regulators have often allowed — inspections and repairs to be delayed for months until scheduled refueling outages. Again and again, problems worsened before they were fixed. Postponed inspections inside a steam generator at Indian Point allowed tubing to burst, leading to a radioactive release in 2000. Two years later, cracking was allowed to grow so bad in nozzles on the reactor vessel at the Davis-Besse plant near Toledo, Ohio, that it came within two months of a possible breach, the NRC acknowledged in a report. A hole in the vessel could release radiation into the environment, yet inspections failed to catch the same problem on the replacement vessel head until more nozzles were found to be cracked last year.
Finally, here are perhaps the foremost worrisome areas:
BRITTLE VESSELS: For years, operators have rearranged fuel rods to limit gradual radiation damage to the steel vessels protecting the core and to keep them strong enough to meet safety standards.
It hasn’t worked well enough.
Even with last year’s weakening of the safety margins, engineers and metal scientists say some plants may be forced to close over these concerns before their licenses run out — unless, of course, new compromises with regulations are made. But the stakes are high: A vessel damaged by radiation becomes brittle and prone to cracking in certain accidents at pressurized water reactors, potentially releasing its radioactive contents into the environment.
LEAKY VALVES: Operators have repeatedly violated leakage standards for valves designed to bottle up radioactive steam in the event of earthquakes and other accidents at boiling water reactors.
Many plants have found they could not adhere to the general standard allowing each of these parts — known as main steam isolation valves — to leak at a rate of no more than 11.5 cubic feet per hour. In 1999, the NRC decided to permit individual plants to seek amendments of up to 200 cubic feet per hour for all four steam valves combined.
But plants keep violating even those higher limits. For example, in 2007, Hatch Unit 2, in Baxley, Ga., reported combined leakage of 574 cubic feet per hour.
CRACKED TUBING: The industry has long known of cracking in steel alloy tubing originally used in the steam generators of pressurized water reactors. Ruptures were rampant in these tubes containing radioactive coolant; in 1993 alone, there were seven. Even today, as many as 18 reactors are still running on old generators.
Problems can arise even in a newer metal alloy, according to a report of a 2008 industry-government workshop.
CORRODED PIPING: Nuclear operators have failed to stop an epidemic of leaks in pipes and other underground equipment in damp settings. The country’s nuclear sites have suffered more than 400 accidental radioactive leaks during their history, the activist Union of Concerned Scientists reported in September.
Plant operators have been drilling monitoring wells and patching hidden or buried piping and other equipment for several years to control an escalating outbreak.
Here, too, they have failed. Between 2000 and 2009, the annual number of leaks from underground piping shot up fivefold, according to an internal industry document obtained and analyzed by the AP.
I coauthored a CNN opinion piece in March that said “The U.S. government and nuclear industry must take new actions to ensure that nuclear power is safe for the American public.” I think the U.S. National Academy of Sciences should be tasked with a full review of nuclear safety. The NRC does not appear up to the job.